Schedule & Funding SCHEDULE & FUNDING

The first brief bridge closure took place on April 25, 2012. During the several day closure, crews demolished the existing approach spans and connected the temporary ramps to the existing bridge. (details).  A tentative timeline for other project activities is below:

how much will the project cost?

Original construction estimates put the cost of replacing the Milton-Madison Bridge at approximately $131 million. The low bid submitted by Walsh Construction Company was for $103 million,  20 percent below the original estimate.

In February 2010, the project was awarded $20 million in funding under the American Reinvestment and Recovery Act. Indiana and Kentucky have identified state and federal funding for the remaining cost of the project, which will be evenly split by both states. Construction is projected to create or preserve 1,400 jobs.

project timeline

  • June 2008 – Project Kickoff
  • Fall 2008 – Public Involvement process begins
  • February 2010 – Project receives federal environmental approval
  • June 2010 – Project contract advertised
  • September 2010 – Contract awarded to Walsh Construction
  • November 2010 – Project groundbreaking ceremony
  • January 2011 – Construction begins
  • April 2012 – First brief closure
  • June 2012 – First span lift

video